Business Days Calculator

Count working days between dates, or add business days.

What do you want to do?

National public holidays only. Regional holidays and observance rules vary, so double-check the list.

Dates as YYYY-MM-DD, separated by commas or new lines, with an optional name after each. To work on a country holiday, add it with a minus sign: -2026-12-26. Holidays on a weekend are not counted twice.

Business days

52 business days

There are 52 working days from Wednesday, 21 October 2026 to Thursday, 31 December 2026, counting both dates.

Calendar days
72 days
Weekend days skipped
20 days (Saturday and Sunday)
Holidays skipped
None entered

Islamic and other lunar holidays are calculated ahead and can move by a day, and governments sometimes add one-off holidays. Check official announcements for exact dates.

Fix the highlighted field to update the result.

Country holiday data: date-holidays (commenthol), from Wikipedia, CC BY-SA 3.0.

How to use

  1. Choose Count business days or Add or subtract business days.
  2. Enter the dates, or a start date and a number of business days.
  3. Pick your weekend, then a country to skip its public holidays. Add any other dates of your own.
  4. Read the result and the days that were skipped.

Formula: how business days are counted

business days = calendar days − weekend days − holidays on working days
  • Counting: both the start and end dates count by default, the same as Excel’s NETWORKDAYS. You can count only one of them, or neither.
  • Adding: the start date is day 0, as in Excel’s WORKDAY. Day 1 is the next working day.
  • Holidays are skipped only if they fall on a working day, so none is removed twice.

Examples

These match Microsoft’s own examples for Excel:

  • 1 October 2012 to 1 March 2013: 110 business days. Skipping 22 November 2012, 4 December 2012 and 21 January 2013 leaves 107.
  • 151 business days after 1 October 2008: 30 April 2009, or 5 May 2009 with those three holidays.
  • 1 business day after a Friday is the following Monday. 5 business days after Friday 23 October 2026 is Friday 30 October.

Country holidays

Choose a country and its national public holidays for this year and the next two are skipped. The list loads from this site only when you pick a country.

  • Regional holidays vary. US states, Canadian provinces, Australian states and Indian states add their own, so add those dates yourself.
  • Lunar holidays can move. Eid and other Islamic holidays are calculated ahead and can shift by a day after the moon is sighted.
  • Governments add one-off holidays. Scotland’s bank holiday on 15 June 2026 isn’t in the list, for example.
  • Working on a holiday? Type it with a minus sign, such as -2026-12-26, to count it as a working day.

Business days in 2026

No holidays removed.

Month Sat–Sun weekend Fri–Sat weekend
January 22 21
February 20 20
March 22 23
April 22 22
May 21 21
June 22 22
July 23 22
August 21 22
September 22 22
October 22 21
November 21 22
December 23 23
Year 261 261
Choosing the start and end options
  • Count both: the usual choice for “working days in this period”.
  • Count the end date only: working days after the start date, up to the end. Use it for “how many working days until”.
  • Count neither: only the days strictly between the two dates.

A contract may define “business day” or “within 5 business days” in its own way, so check the wording. Holidays are skipped only for the country you choose and the dates you type.

Holiday data comes from the open-source date-holidays project, which compiles Wikipedia’s lists (CC BY-SA 3.0). We checked the US list against OPM’s federal holidays and the UK lists against GOV.UK for 2026 and 2027.

To add calendar days instead, use the date calculator. To count every day, use the days between dates calculator.

Frequently asked questions

How many business days are between two dates?

Count the days from start to end, then remove weekend days and holidays. For example, 1 October 2012 to 1 March 2013 has 110 weekdays, both dates included.

Are public holidays excluded?

Yes, if you choose a country: its national public holidays are skipped. You can also type extra dates, or keep a holiday as a working day. Regional holidays vary, so double-check.

What does “within 5 business days” mean?

Usually the fifth working day after the start date, which counts as day 0. From a Friday, that is the next Friday if there are no holidays. Check your contract’s definition.

Are the start and end dates counted?

Yes, both are counted by default, matching Excel NETWORKDAYS. You can choose to count only one of them, or neither.

Can I use a Friday–Saturday weekend?

Yes. Choose the weekend that applies to you, including Friday–Saturday, Thursday–Friday, Sunday only or Saturday only.